All the information related to our products at your disposal:
Uncategorized
Last January, an extraordinary and powerful short-circuit caused the circuit breakers at the Yéchar substation in Murcia (from Confederación Hidrográfica del Segura) to break, leaving the Mayés dam and several canals, among others, without electricity supply.
Ormazabal collaborated with EPPA INGENIERIA and the Confederación Hidrográfica del Segura (CHS) on the grid repair and network restablishment works, with the supply of medium voltage equipment for the Rambla de Algeciras transformer substation as a matter of urgency and within the necessary timing. Ormazabal provided the transformer substation, consisting of a pfu type concrete prefabricated enclosure equipped with cgmcosmos cubicles, in which a separately supplied 630 kVA transformer was installed, which will enable the voltage level to be increased from 10 kV to 15 kV, thus meeting both grid requirements and the client’s needs.
As a result of this incident, the Mayés dam started to operate with the emergency systems, which entailed potentially serious risks for people and assets. Likewise, the entire operating, regulation and flow supply capacity for irrigation and the essential public supply service to various cities in the region was lost, with the repair of the Yéchar substation and the medium and low voltage installations of the main canal on the right bank of the Tagus-Segura Distribution Canals being declared an emergency.
Share this post
Nombre
Departamento
Unidad de negocio:
¿Por qué te interesa formar parte del equipo LEAP?
¿Qué experiencia o perspectiva crees que puedes aportar al equipo?
¿Has participado anteriormente en iniciativas relacionadas con la igualdad de género o diversidad?
¿Tienes disponibilidad para participar en reuniones periódicas (presenciales o virtuales)?
🗣 ¿Hay algo más que te gustaría compartir o proponer en relación con esta iniciativa? (Este espacio es libre para cualquier idea, sugerencia o reflexión que quieras aportar.)